Response to RFA No. 23/2026 under Articles 14 and 14.4 of the IICRA Rules
To: The International Islamic Center Of Conciliation and Arbitration in Dubai By the Respondent
Appendices

Agreements Signature 18-02-2019
- License Agreement
- Master Services Agreement
- Appendix (A) to Master Services Agreement
- Statement of Work 1
The License Agreement Covers 13 Systems (All in blue clickable for overview):
- ESKA Credit Insurance System
- ESKA Bancassurance System
- ESKA Customer Portal
- ESKA Financial Management System
- ESKA Agent Portal
- ESKA Incident Management System (IMS)
- ESKA Document Management System (DMS)
- ESKA Customer Relationship Management (CRM)
- ESKA Approval System
- ESKA Notifications System
- ESKA Intelligence and Analytics Systems (Logging - Audit Trail - Analytics)
- ESKA Workflow Management System
- ESKA Takaful - Wakala Insurance System
- ICIEC_Agent Portal_BRD_Signed
- ESKA_CRM Business Processes_Signed
- ICIEC_Agent Portal_Business Processes_Signed
- ICIEC_Banc-assurance_BRD_Signed
- ICIEC_Credit Insurance_BRD v7_BPD v5_Annex to the BRD_Signed
- ICIEC_Banc-assurance_Business processes_Signed
- ICIEC_Customer Portal_Business Processes_3_Signed
- ICIEC_Customer Portal_BRD_2_Signed
- ICIEC_CRMSystem_Gap Scope Document_Signed
- ICIEC_Financial System_Business Processes_2_Signed
- ICIEC_Financial System_Gap Scope Document_4_Signed
- ICIEC_Financial Integration Document_3_Signed.docx
- ESKA_Credit Insurance Business Processes_5
- ICIEC_Credit Insurance_BusinessRequirementsDocument_v7
- ICIEC_Provisional Acceptance_Signed
- ICIEC Verification Log Sheets
- ICIEC_Bank_Portal_Gap Verification Log Sheet_2
- ICIEC_Agents_Portal_Gap Verification Log Sheet_2.xlsx
- ICIEC_Financial System_Gap Verification Log Sheet_2
- ICIEC_Customer_Portal_Gap Verification Log Sheet_3
- ICIEC_Credit_Gap Verification Log Sheet_5
- Systems
- Insurance
- Credit Insurance
- ICIEC_TrainingSyllabus_Credit Insurance_Commercial Production_Signed
- ICIEC_TrainingSyllabus_Credit Insurance_Claims_Signed
- ICIEC_TrainingSyllabus_Credit Insurance_Country Risk_Credit Information_Signed
- ICIEC_TrainingSyllabus_Credit Insurance_Reinsurance_Signed
- ICIEC_TrainingSyllabus_Credit Insurance_Sovereign Production_Signed
- ICIEC_TrainingSyllabus_Credit Insurance_Reinsurance_XoL_Signed
- ICIEC_TrainingSyllabus_CustomerPortal_2_Signed
- ICIEC_TrainingSyllabus_AgentsPortal_2_Signed
- ICIEC_Training Syllabus_Approval and Notifications_Signed
- ICIEC_TrainingSyllabus_Bancassurance_3_Signed
- ICIEC_Training Syllabus_Wakala Module_1_Signed
- Credit Insurance
- Enterprise
- RAD
- Security & Analytics
- Insurance
- ICIEC Training Acceptance Signed
- ICIEC_Core Administration_UAT re-validation_Passed_2022
- ICIEC_Logging_Audit Trail_BI_UAT Revalidation_Passed_2021
- ICIEC_CRM and IMS_UAT Results_Passed_2022
- ICIEC_Financial System_UAT Results_AR_Cash M_Shareholder_AR_Passed_2022
- RE ICIEC_DMS_UAT Revalidation_Passed_2021
- ICIEC_Approval and Notification_UAT revalidation Results_Passed_2022
- ICIEC_Credit Insurance_Commercial Production_UAT Results_2023
- ICIEC_Credit Insurance_Credit Information_UAT Results_Passed_2022
- ICIEC_Credit Insurance_Country Risk_UAT Results_Passed_2022
|
|
Activity | Milestone |
Date | Duration |
|---|---|
Project Kick off Meeting |
07 Apr 2019 |
Project Charter Sign-off by ICIEC |
11 Apr 2019 |
Gap Analysis |
Apr 2019 – Oct 2019 |
Original Scope Definition & Sign-off by ICIEC |
Dec 2019 – Feb 2020 |
Customization |
Sep 2019 – Jan 2020 |
Systems Installation at ICIEC Azure Test Environment |
Jan 2020 - Feb 2020 |
Setup Configuration |
Jan 2020 – Apr 2020 |
Gap Verifications |
Mar 2020 - Apr 2020 |
ICIEC requested additional changes to the original scope (CR 01_2020) |
25 Jun 2020 |
Provisional Acceptance Signed by ICIEC on the Original Scope |
15 Jul 2020 |
Systems Installation at ICIEC Azure Production Environment |
Aug 2020 |
Training |
Sep 2020 – Dec 2021 |
Training Acceptance Signed by ICIEC |
12 Dec 2021 |
User Acceptance Test * Credit Insurance & Portals UAT Paused by ICIEC for Credit Insurance & Portals |
Sep 2020 – Jul 2022 |
ICIEC requested additional changes CR 01_2021, CR 01_2022 & CR 01_2024 •ICIEC didn’t renew ESKADENIA user accounts Password
•ICIEC has locked ESKADENIA’s user accounts in 2025 |
CR 01_2021: 28 Mar 2021 CR 01_2022: 27 Jun 2022 CR 01_2024: 20 Feb 2024 |
Original Scope is Completed & Delivered in 2020
yet
Closure of the Original Agreement is being withheld by ICIEC
| Change Request | Man-days | Status |
|---|---|---|
| 308 |
100% Verification Completed as per the signed CR scope document CR Verification Acceptance Signed by ICIEC on 26 Jun 2024 |
|
| 259.2 | 100% Verification Completed as per the signed CR scope document | |
| 680 | 100% Verification Completed as per the signed CR scope document | |
| 1237 | 100% Verification Completed as per the signed CR scope document |
- Out of the total of 462 CR points, ICIEC has approved 445, BUT requested additional changes on 17 points of the approved CRs,
- Additional Changes were requested by ICIEC as a result of the completed data migration reconciliation sessions.
- Hundreds of points (changes) were developed by ESKADENIA and delivered to ICIEC at no extra cost.
- All Change Requests were delivered as per the Signed Scope Documents and even beyond a stretched scope.
- The current pressing issue is that another list of additional requirements is needed by ICIEC and is regarded as a prerequisite before going live.
- ICIEC_Announcement_ESKADENIA New Enterprise Business Unit Manager_10 Jan 2024
- ICIEC_Announcement_ESKADENIA Project Team_Resource Change Note_29 Aug 2021
- ICIEC_Announcement_Credit Insurance_New BA Resource_24 Oct 2024
- ICIEC_Announcement_New ESKADENIA Security and Analytics Business Unit Manager_20 Feb 2023
- ICIEC_Announcement_New ESKADENIA Security and Analytics Business Unit Manager_20 Feb 2023_
- Provisional Acceptace Letter
-
Statement of Account / Financials Counterclaim
Statements of Account
Financials Counterclaim
- CEO Letter Nael Saleh - 1st of January 2023
- CEO Letter Nael Salah - 8th of January 2023
- ESKA CEO Letter 9th March 2023
- CEO Letter Nael Salah - 12th of July 2023
- CEO Letter Nael Salah - 24th of Oct 2023
- CEO Letter Nael Salah - 8th of Nov 2023
- ESKA CEO Letter 28th November 2023
- ESKA CEO Letter 18th December 2023
- ESKA CEO Letter 2nd January 2024
- ESKA CEO Letter 15th April 2024
- ESKA CEO Letter 22 May 2024
- Final Legal ICIEC CEO Letter 23 July 2025
- ESKA CEO Letter 14th August 2025 (Counterclaim)
- ESKA CEO Letter 15 October 2025
ICIEC has failed to commit to the project with an absence of " ineffective IT leadership and administration, the internal misinformation between the IT and the business leaders lead to this misfortunate stop of a successful product. None that ESKADENIA is responsible for. " Quote by ESKADENIA
- The uncontrolled, continued requests for out-of-the-scope requirements have highly impacted the project planned schedule, key milestones and going live.
- None of the additional requirements requested by ICIEC are proven (with evidence) to be within the scope.
Failure to Commit to The Signed and Agreed Scope
Example is of the Appendix A to the master services agreement and to the signed scope of the BRD, and the CRs (CR 01_2020, CR 01_2021, CR 01_2022 & CR 01_2024) with continued requests of additional requirements that are out-of-the-scope throughout the past 5 years.
ICIEC Failed to comply with Appendix A to the Master Agreement
– Section 7 Scope Change Requests
“Management of scope needs to be strictly enforced. All project team members should ensure that they are familiar with the scope and ensure that the design and deliverables remain within the boundaries of this scope.”
On Changes of Personnel
- ESKADENIA has informed the ICIEC IT team ( Mohamad El-Sayed & Reyaz Wani) with changes in ESKADENIA’s consultants by email throughout the project duration.
ICIEC Failed to comply with Appendix A to the Master Agreement
– Section 3 Data Lifecycle Management (Actions by ICIEC) “Data cleansing: Purging the obsolete data based on rules to be defined,
- Correcting the data in the existing System(s),
- Completing the missing data in the existing System(s),
- Archiving the data, if need be based on rules to be defined”
- ICIEC_ITS_Technical Meeting_discuss CRs and Data Migration remarks justification_Apr 2025
- RE ICIEC ITS Technical Meeting to discuss remarks justification_MoM_14 Apr 2025_ESKA Reply1
- RE ICIEC ITS Technical Meeting to discuss remarks justification_MoM_14 Apr 2025_ESKA Reply2
- ICIEC Takaful System_Progress Report_11122024_08042025
- ICIEC_Technical Meeting_ESKADENIA Position Basis_14 Apr 2025
- ICIEC_Insurance Data Migration Reconciliation_Progress Report_20 Mar 2025
- ICIEC_Insurance Data Migration Reconciliation_Progress Report_08 Apr 2025
- ICIEC_TakafulSystem_ProgressReports
- Agree to amicably end the cooperation and part ways,
- Agree on a solution and work together for project success, which turned impossible as more change requests kept comming
- ESKADENIA claims financial payment as stated in our last letter.
- We could agree on a reasonable price to license the Intellectual Property (Source Code) of the Credit Insurance System for ICIEC internal use.
- We could agree on the smooth transfer of the Intellectual Property (Source Code) and associated competence development of ICIEC IT staff.
- We would be available as technology consultants for a certain period of time if needed.
- ESKADENIA needs the pending payments of the Original Agreement and the four Change Requests and additional efforts’ costs to be settled.
- We would agree on a final Change Request to be signed ahead of going live.
- ESKADENIA will put all its efforts and competent resources to close this final Change Request in record time.
- We need the good will of ICIEC to push for a speedy project closure.
- ESKADENIA's (The Respondent) Reponse to the RFA 23-2026 Reffrence to IICRA Rules 14 and 14.4
- The Respondent reserve their right to to request all sorts of evidences mentioned and permitted through the IICRA rules Article (43) including but not limited Experts Opnion throught inspection and auditing over the systems through an independent experties.